sls: dimensional accuracy
use the information below to answer the questions

bin cool down
laser powder filament fabrication, there is a possibility of shrinkage or warpage in sls printing. this is caused by differential cooling that occurs as each layer is printed.

the time it takes the powder bin to fully cool down after running a build can be up to 50% of the entire build time. during this cooling period, the form is often quite prone to warping.

reducing shrinkage and warpage
in extreme situations where the temperature gradient in a build causes material warpage, an edge may curl high enough to block the path of the re - coater arm. if the arm makes contact with the printed form, this can cause serious damage to the machine. there are several ways to prevent that from happening:

  • when the laser sinters the powder, the area where the laser beam is making contact with the material is much hotter than the portion of the powder bin down below, where the material has had time to cool. to diminish the temperature gradient, the powder bin is heated which creates a more stable environment for the powder and reduces the possibility of warpage or shrinkage.
  • another technique used to prevent material warpage is to change the orientation of the part. instead of having flat planes parallel to the print bed, forms can be positioned at various angles or printed vertically. this reduces the cross - sectional area and the amount of internal stresses that can be created in each layer.

what can take up to 50% of the entire build time of an sls print?

  • the time it takes for the printer to re - coat the powder
  • loading the materials into the printer
  • positioning the mirrors for the laser
  • the time it takes the powder bin to fully cool

Explanation:

Brief Explanations

We refer to the text in the "Bin Cool Down" section which states "The time it takes the powder bin to fully cool down after running a build can be up to 50% of the entire build time". By comparing this with the given options, we can find the correct answer.

Answer:

the time it takes the powder bin to fully cool