Question
please fill in the blank below.
in an adaptive approach, plans are more iterative than structured, and these projects go in the direction of what customer ____ dictates.
Brief Explanations
Adaptive project management approaches prioritize iterative planning that aligns with ongoing customer needs and feedback, so the blank refers to the customer's stated or expressed requirements.
Snap & solve any problem in the app
Get step-by-step solutions on Sovi AI
Photo-based solutions with guided steps
Explore more problems and detailed explanations
requirements