11 multiple choice 1 point for the construction of new stands inside a …

Question

11 multiple choice 1 point for the construction of new stands inside a gymnasium, which project task is considered to be a procurement? securing the internal designers availability to design the stands starting the bid process for a vendor to build the stands finalizing a contract to build the stands obtaining the wood to build the stands.

Explanation:

Brief Explanations

Procurement is about acquiring goods or services. Obtaining wood is acquiring a good for construction.

Answer:

D. Obtaining the wood to build the stands