a project to build a new library is behind schedule. which a part of th…

Question

a project to build a new library is behind schedule. which a part of the project plan will have the best chance of putting the schedule back on track?

options

increasing the number of quality inspections on the building

adding an additional team of builders to the project

increasing the project budget by 10%

removing a task to plant a garden

Explanation:

Brief Explanations

This adjustment directly increases the labor capacity dedicated to constructing the library, which is the most direct way to accelerate work and make up for the delayed schedule. Reducing quality inspections risks long-term issues, a budget increase alone doesn't guarantee faster work without allocating it to labor, and removing a non-critical task (garden) will not address the core construction delay significantly.

Answer:

Adding an additional team of builders to the project.