a project to build a new library is behind schedule. which a part of the project plan will have the best chance of putting the schedule back on track?
options
increasing the number of quality inspections on the building
adding an additional team of builders to the project
increasing the project budget by 10%
removing a task to plant a garden
This adjustment directly increases the labor capacity dedicated to constructing the library, which is the most direct way to accelerate work and make up for the delayed schedule. Reducing quality inspections risks long-term issues, a budget increase alone doesn't guarantee faster work without allocating it to labor, and removing a non-critical task (garden) will not address the core construction delay significantly.
Snap & solve any problem in the app
Get step-by-step solutions on Sovi AI
Photo-based solutions with guided steps
Explore more problems and detailed explanations
Adding an additional team of builders to the project.